Cutoff Dates for Fiscal Year 2024 Purchases
FSIS Notice
61-23
Issue Date
Nov 06, 2023
Expiration Date
Nov 01, 2024
Full Notice
- PURPOSE
This notice establishes Fiscal Year 2024 cut-off dates for processing procurement requests, interagency agreements (IAAs), and cooperative agreements (CAs). These cut-off dates ensure that the Agency can obligate its funds in a timely manner through acquisitions by September 30, 2024. These dates will aid Program Areas in planning purchases throughout the year. - PROGRAM OFFICE RESPONSIBILITY
- Program Areas are to send completed purchase request packages entered into the Integrated Acquisition System (IAS) to the Office of Management (OM) Administrative Services Division (ASD), Procurement Management Branch by the cut-off dates listed in below for the referenced dollar amounts. The dollar amounts identified below include option years, if any. Contents of a complete requisition package can be found in FSIS Directive 2100.1, Procurement of Supplies, Equipment, and Services.
- To avoid processing delays, program areas are to ensure requisitions submitted into the Integrated Acquisition System include the following:
- In the Description box:
- Detailed description of product or service;
- State “Option Year Renewal” if you are exercising an option year or “Additional Funding” if adding funds to an existing order and provide award number to be modified;
- If services are being procured, provide the name of the Contracting Officer Representative (COR) to be appointed; and
- Excepted or Non-Excepted: State in description if the requirement is excepted or non-excepted in the event of a government shutdown. (Excepted means essential and needs to continue in the event of a government shutdown; Non-Excepted means non-essential and work will stop if there is a government shutdown). The Chief Operating Officer can provide clarification as to whether a procurement is excepted or not).
- Supporting documentation: Ensure all quotes, attachments, Statement of Work/Performance Work Statements and Acquisition Plans are attached prior to submitting the requisition.
- In the Description box:
- Program Areas are to ensure that requisitions are moving through all processes to allow sufficient time to coordinate approvals.
- Program Areas are to obtain pre-procurement approvals as early as possible in the procurement process.
- The requisitioner is to obtain approvals for information technology requirements, including receipt of Acquisition Approval Requests, in accordance with USDA Office of the Chief Information Officer policy.
- Program Areas shall review the USDA Contracting Desk Book, Part 407 regarding Acquisition Planning to determine if applicable.
- Contract award before the end of the fiscal year is not guaranteed for requisitions submitted after these established cut-off dates or if an incomplete package is submitted.
- Program purchase card holders should make sure USBank transactions are reconciled by the date below. If the transaction cannot be reconciled due to goods/services not being received, program office are to account for the charges on the Period End Estimate form provided by the Budget Office.
- LATE REQUISITIONS
Requisitions received after the cut-off date are considered late and may not be processed. Program offices are to follow these instructions if there is a late requisition:- Enter requisition in IAS;
- Prepare a late requisition approval request memo, which is to be signed by the Assistant Administrator (AA) of the respective Program Area and submitted to the OM AA;
- Send late requisition procurement request emails to: FSISProcurement@usda.gov;
- The ASD Procurement Management Branch will review the requisition package to ensure that it is complete;
- If the package is complete, ASD will validate and forward it to the OM AA for approval; and
- If it is not complete, the ASD Contracting Officer is to notify the requisitioner that no action can be taken until the procurement package is complete. Late requisitions will be returned unprocessed.
- QUESTIONS
Refer questions about this notice or for assistance with acquisition planning, to: FSISProcurement@usda.gov.
ATTACHMENT -FISCAL YEAR 2024 CUT-OFF DATES
PROCUREMENT CUT-OFF DATES | ||
REQUIREMENT | DOLLAR AMOUNT | CUT-OFF DATE |
All Supplies, Equipment, and Services (Dollar values should be inclusive of base year and all option year totals.) |
$4 million and above | February 8 |
$600,000, but less than $4 Million | March 7 | |
$250,000, but less than $600,000 | April 4 | |
$25,000, but less than $250,000 | May 2 | |
Less than $25,000 | July 25 | |
Up to the Micro Purchase Threshold Supplies/equipment up to $10,000 and Services up to $2,500 |
September 5 (Use Program Area's Purchase Card) | |
Reconciliation of Purchase Card Transactions | September 12 | |
Final Mission-Critical Investments (MCIs) (Approved by Management Council) | June 27 |
INTERAGENCY AGREEMENTS CUT-OFF DATES | |
Action Type | Date |
IAAs to FedSim/FedSource or other franchise funds | June 6 |
IAAs under the Economy Act when the performing agency will use Government employees to accomplish the work | June 6 |
All other IAAs (i.e., Economy Act orders when the performing agency will contract out the work) | July 11 |
COOPERATIVE AGREEMENTS CUT-OFF DATES | |
Action Type | Date |
All new CAs | June 27 |
Non-competing continuations | August 1 |